Contractor given until March to complete Loon Hospital

Topic |  

Contractor given until March to complete Loon Hospital

Topic |  
 ADVERTISEMENT 

The contractor of the long-delayed Congressman Natalio Castillo Memorial Hospital (CNCMH) in Loon was given a deadline by Governor Aris Aumentado to complete, or at least finish key segments of the P80-million facility, to allow it to start operations by March this year.

According to Provincial Engineering Office chief Camilo Gasatan, officials of Manila-based Medikotek, Inc. were told by Aumentado to expedite the completion of the project, which was first conceptualized during the post-earthquake rehabilitation efforts under the Aquino administration in 2013.

The Medikotek officials met with Aumentado earlier this week and were asked to provide a status report on the project.

“Dili man pud sa ingon na gituok sila og maayo. Gi hatagan sila og chance ni governor na dili na paabton og March. Giingnan nato sila na hospital ni, dili ingon na ordinary infrastructure, unya luoy na ang sitwasyon sa atong daan na hospital kay naguba baya to sa linog pa,” said Gasatan.

 ADVERTISEMENT 

Based on the contractor’s report, the facility was estimated to be “80 to 90 percent” complete.

Gasatan said that the entire facility need not be fully complete by March as long as it can already start to accommodate patients.

“Atong trabahuon na bahal og dili pa siya makompleto pero magamit na ba. Bahalo og dili ingon na 100 percent, basta magamit na nato,” he added.

Medikotek was asked to submit a commitment letter as it vowed to increase their labor workforce and hasten the delivery of materials.

“Gipacommit gyud nato sila mao ng mopada sila og commitment letter kay di man mag silbi og magstorya ra ta ani so mohatag sila dapat og commitment,” said Gasatan.

Officials of the construction firm explained that the project was delayed due the increase in prices of materials for the project and the slow delivery of these items from Luzon to Bohol.

 ADVERTISEMENT 

They also noted further slowdown in the construction due to the COVID-19 pandemic which crippled inter-island transportation and the effects of Typhoon “Odette” which pummeled Bohol in December 2021.

 ADVERTISEMENT 

According to Provincial Health Office (PHO) chief Dr. Reymoses Cabagnot, new equipment for the hospital has already been acquired and are ready to be installed in the facility once it is completed.

However, more pieces of equipment may still be required depending on the recommendation of the Department of Health (DOH).

“Nagpa-reassess na ko sa DOH adtong December sa tanang hospitals og basin naay lain panginahanglanon pa na wa pa ma apil sauna, lain na pud ng estorya,” he said.

 ADVERTISEMENT 

Construction of the health facility was supposed to start in 2016 but it pushed through only in 2019 when former Governor Edgar Chatto was already about to step down from office.

It took a while for construction to start as the government had difficulty in finding a location which meets the safety standards set by the Mines and Geosciences Bureau (MGB).

 ADVERTISEMENT 

The MGB refused to issue a clearance for the construction of the new facility at the same site of the old quake-hit CNCMH as it was deemed unsafe. (A. Doydora)

Be First to Comment

Leave a Reply